M.Kazarinov =========== Dubna status report 1. Module CF-17 delivered to CERN 7.06.99 2. Copper plates production. Copper plates for CF-19 should be finished 10.07.99 Copper plates for CF-20 15.08.99 3. Stailess steel items for Modules CF-18 - CF-20 will be finished 10.07.99 4. Clean room. One week humididy test. 12.07.99 5. Plans for 1999 : 5.1 Assembly 1 serial and 2 special modules 5.2 Copper and SS parts delivery to MPI: 2 sets in August , 2 sets in January next year 5.3 Bring 3 modules to CERN in December 5.4 Cold test February next year